Detailed Multi-Project Critical Chain Demonstration Video index |
|
Time |
Description |
00:00 | Introduction to Demonstration |
00:35 | Description of Current States |
Summary Projects | |
1:20 | Initial scheduling with safe durations and aggressive durations |
1:40 | First time scheduling |
Unsuccessful initial scheduling | |
Explanation of ‘ambitious projects’ | |
2:38 | Resource conflicts |
Electrician and Mechanics conflicts | |
4:00 | Set as tracking resources so scheduling system won’t level resources |
Reschedule after tracking resources | |
4:50 | Changing each resource to be optimizable |
Optimize Resource Usage | |
5:40 | Histogram plot |
6:03 | Hiding downtime |
6:38 | Editing Activity in Histogram Plot |
7:50 | Viewing Gantt Chart |
Loading different border color project rule set | |
9:04 | Switching into aggressive mode |
9:45 | Viewing PERT again |
Critical Chain calculated on a per-project basis | |
10:01 | Inserting Buffers |
Viewing Feeder buffers in Gantt chart | |
10:50 | Analyze Progress for the first time, Focusing on Dynamic Critical Chain running through the whole factory |
11:12 | Adding section for Dynamic Critical Chain in Gantt Plot Configuration |
12:10 | Detailed explanation on Dynamic Critical Chain grouping |
14:00 | Configuring Label display in Gantt chart |
14:53 | Criteria for Dynamic Critical Chain priority |
15:27 |
Task Priority Report Finding current highest priority |
16:10 | Completing first two jobs and analyzing progress |
17:02 | Viewing Buffer Incursion Report |
17:50 | Seeing flow of control and dependencies in localized PERT chart |
18:50 | Looking at Spatial Plot on Project Level |
19:06 | Loading custom criteria to view field by project |
19:55 | View Constraint Analysis report to find project bottlenecks |
20:48 | View Histogram Plot to see resource usage |
21:57 | Using Gantt Chart to view relationships across projects |
22:57 | Inter-project “swap offs” |
23:45 | Linkage of Temporal Relationships between projects |